| SECTION 7 - EARTHWORKS |
| Excavation |
320,580 m3 |
| Formation preparation |
704,990 m2 |
|
| SECTION 7 - FLEXIBLE SURFACING |
| Interlock Tiles |
504,780 m2 |
| Asphalt (Base & Wearing Course) |
260,174 m2 |
| Road Marking |
99145 l.m
|
| Traffic Signs |
1761 No. |
|
| SECTION 7 - KERBING |
| Raised, Flush, Edge & Dropped Kerbs |
197,317 l.m |
|
| SECTION 7 - STREET LIGHTING WORKS |
| Light Poles |
1735 No. |
| Cabling |
85,090 l.m |
| Ducts |
30,215 l.m |
|
| SECTION 10 - SURFACE WATER DRAINAGE |
| Manholes |
835 No. |
| Gullies |
3441 No. |
| Pipe Lines & Gully Line |
48403 l.m |
| Trench Soak-away |
36274 l.m |
| Microtunling |
1608 l.m |
|
| SECTION 11 - SEWERAGE WORKS |
| Pipe Line Including house connections |
1315 l.m |
| Manholes |
47 nr |
|
| SECTION 12 - TSE |
| HDPE Pipe Line |
10777 l.m |
| Chambers |
86 nr |
|
| SECTION 13 - ELECTRICAL WORKS |
| LV Cabling |
3800 l.m |
| Ducts |
4500 l.m |
|
| SECTION 13 - Q - TEL WORKS/QNBN |
| PVC Ducts |
112360 l.m |
| Chambers |
669 No |
|
| SECTION 13 - QGE & WC (WATER WORKS) |
| Pipe Lines Dia. 100mm to 300mm |
4408 l.m |
|